# Fedora 20
#
# Copyright 2011 John Poelstra <poelstra@fedoraproject.org>
# Copyright 2011 Robyn Bergeron <rbergero@fedoraproject.org>
#
# Permission is hereby granted, free of charge, to any person
# obtaining a copy of this software and associated documentation files
# (the "Software"), to deal in the Software without restriction,
# including without limitation the rights to use, copy, modify, merge,
# publish, distribute, sublicense, and/or sell copies of the Software,
# and to permit persons to whom the Software is furnished to do so,
# subject to the following conditions:
#
# The above copyright notice and this permission notice shall be
# included in all copies or substantial portions of the Software.
#
# THE SOFTWARE IS PROVIDED "AS IS", WITHOUT WARRANTY OF ANY KIND,
# EXPRESS OR IMPLIED, INCLUDING BUT NOT LIMITED TO THE WARRANTIES OF
# MERCHANTABILITY, FITNESS FOR A PARTICULAR PURPOSE AND
# NONINFRINGEMENT. IN NO EVENT SHALL THE AUTHORS OR COPYRIGHT HOLDERS
# BE LIABLE FOR ANY CLAIM, DAMAGES OR OTHER LIABILITY, WHETHER IN AN
# ACTION OF CONTRACT, TORT OR OTHERWISE, ARISING FROM, OUT OF OR IN
# CONNECTION WITH THE SOFTWARE OR THE USE OR OTHER DEALINGS IN THE
# SOFTWARE.
#
# Current release version
macro major [20]
# Last release version
macro previous_major[19]
# Next release version
macro next_major [21]
# do not change this
macro content [f]
# do not change this
macro content_title [Fedora]
# GA date of previous release
macro start_date [2013-04-30]
# set to one day after "start_date"
macro start_work [2013-05-01]
macro end_date [2014-12-31]
macro prior_project [f19]
project ${content}${major} "${content_title}" "${major}" ${start_date} - ${end_date} {
timeformat "%Y-%b-%d"
# Based on Eastern time zone in USA
timezone "America/New_York"
# Setup scenarios
scenario plan "Original Plan" {
scenario actual "Actual"
}
# Limit working days
workinghours sat,sun off
}
# ========= Cornerstones of Fedora Schedules =============
# This section also serves as a "style guide" for the source file too
/*
1) EVERY entry should be in the following line order and indented consistently with the rest of the file. This makes the source file consistent and easier to read.
a) task name and description
b) dependency (if applicable)
c) length (not "duration") (if applicable)
d) flags (if applicable)
2) Official Release Engineering Composes happen on Thursdays, except for the final release
3) Syncing releases to mirrors ideally happens on Thursdays... end of day on Friday is worst case
4) Most tasks are scheduled with 'length' instead of 'duration' to get a sense of "work days" required--using 'length' one week = 5 days
--an eternal debate could be held to discuss whether or not schedule calculations
should include weekends because community members work at all times and not within strict work days.
5) Use "length" everywhere and "duration" only when something must take into account a weekend day
6) All "Blocker Bug Days" should be on Fridays
7) If a task takes one day or less--schedule with no length--this way it shows up as a milestone and gets included in iCalendar (ics) file
8) Because of bugs in the way TaskJuggler ics files get rendered in some calendars (e.g. Zimbra) we only include zero length (milestone) tasks in the ics file. As a result there are several duplicate tasks with no length that have been added so they appear in the ics file.
9) Use core schedule milestones (flags = key) as anchor points (depends/precedes) for tasks in this schedule file instead of more transient tasks like meetings, compose dates, etc. that may change (or slip) from release to release. This makes building new release schedules easier and require less maintenance and updating.
10) In ALL but limited cases task beginning and ending should be automatically calculated based on logic in this file. When using hard coded dates, explicitly call them out with a comment to highlight their existence. Hard coded dates are particularly troublesome when slipping a schedule or branching the file to create a new release schedule because they must be adjusted and recalculated manually
11) TaskJuggler does not provide an easy way (that I am aware of) to schedule tasks to happen *before* other tasks. I've created a hack/methodology I call "shadow" tasks. These are unreported tasks that go backwards a certain period of time and serve as an anchor or starting point for the actual task to be reported.
12) The "milestone" declaration is NOT used in this source file. It is redundant and unnecessary. Do not include it. All tasks without 'length' or 'duration' are automatically considered "milestone" tasks.
*/
# Define flags for filtered reporting
flags ambassadors
flags bugtriage
flags blocker # use to proof blocker meeting placement
flags design
flags devel
flags docs
flags elections
flags fpl
flags hidden # used to hide tasks that we do not displayed in Fedora reports
flags infrastructure
flags interface
flags key /* use for report of key tasks/high level overview--reflected on Fedora wiki, e.g.
https://fedoraproject.org/wiki/Releases/15/Schedule */
flags proto # used for drafting new schedules and shows tasks useful for doing this
flags pm
flags pr
flags marketing
flags roadmap # major milestones
flags translation
flags quality
flags releng
flags spins
flags web
task ${content}${major} "${content_title} ${major}" {
start ${start_work}
task first_day "First Day of Development" {
flags hidden
}
task PlanningPhase "Planning Phase" {
# add for ical
task start_features_cal "Start Feature Submission" {
flags key, pm, roadmap
}
task rawhide_spins "Start Nightly Spins Compose Based on Rawhide" {
depends !!first_day {gaplength 5d}
flags spins
}
# ADJUST FOR NEW RELEASE
# HARDCODED date--approximately 2 weeks after GA of previous release
task file_ticket "File ticket with RHT Eng-ops for Fedora 17 EOL bugzilla closure" {
start 2013-05-15
flags pm
}
# ADJUST FOR NEW RELEASE
# HARDCODED date--approximately 4 weeks after GA of previous release
# this date is approved by FESCo in accordance with https://fedoraproject.org/wiki/LifeCycle
# The process behind this task is at: https://fedoraproject.org/wiki/BugZappers/HouseKeeping
task fedora17_eol "RHT Eng-Ops Fedora 17 EOL auto closure" {
start 2013-05-29
flags pm, key
}
task clean_market_wiki "Cleanup Marketing wiki from previous releases" {
depends !start_features_cal {gaplength 25d}
length 5d
flags marketing
}
task cycle_market_wiki "Cycle Marketing wiki pages for current release" {
depends !start_features_cal {gaplength 25d}
length 5d
flags marketing
}
task bug_trackers "Create Tracker Bugs" {
flags pm
note "See details at https://fedoraproject.org/wiki/BugZappers/HouseKeeping/FirstDayDevel"
}
task design_concept "Conceptual Design Phase" {
length 30d
flags design
}
# ADJUST FOR NEW RELEASE
# a solid start for the wallpaper is the goal for alpha
# adjust length so packaging end date lands on Alpha Deadline
task wallpaper_design "Wallpaper Design for Alpha" {
depends !design_concept
length 35d
flags design
}
} # E N D of PlanningPhase
task supplement_wallpaper "Supplemental Wallpaper Process" {
flags design
# ADJUST FOR NEW RELEASE
# adjust length of this task so that 'package_supplemental_wallpaper' ends on Beta Deadline
task supplement_wallpaper_submit "Supplemental Wallpaper Submission Period" {
length 82d
}
task decide_supplement_wallpaper "Select Official Supplemental Wallpaper" {
depends !supplement_wallpaper_submit
}
task supplement_license_review "Verify Supplemental Wallpaper Licenses" {
depends !decide_supplement_wallpaper {gaplength 1d}
length 10d
}
task package_supplemental_wallpaper "Package Supplemental Wallpaper" {
depends !supplement_license_review
length 2d
}
} # end supplemental wallpaper
task DevelopmentPhase "Development Phase" {
start ${start_work}
task devel_start "Start Development" {
flags devel
}
# ADJUST FOR NEW RELEASE--IMPORTANT
# The length of this task DRIVES THE ENTIRE SCHEDULE
# and determines when the testing phases starts. The testing
# phase of the schedule is static (and completely automatically
# generated by TaskJuggler) from release to release, but the
# number of days of development varies depending when the previous
# release ended (GA). As a result the length of this task also
# influences where the GA date lands.
# Each "5d" (5 days) is equivalent to one week.
task develop "Packaging and Development (precedes Alpha)" {
length 70d
flags devel, proto
}
} # E N D of DevelopmentPhase
task TestingPhase "Testing Phase" {
task alpha "Alpha Release" {
start ${start_work}
task shadow_alpha_blocker "SHADOW: anchor for first blocker meeting" {
precedes !feature_freeze {gaplength 11d}
flags hidden
}
task remind_alpha_blocker1 "Reminder: Alpha Blocker Meeting (${content}${major}alpha) #1" {
depends !shadow_alpha_blocker {gaplength 3d}
flags pm
}
task alpha_blocker1 "Alpha Blocker Meeting (${content}${major}alpha) #1" {
depends !shadow_alpha_blocker {gaplength 5d}
flags releng, quality, devel, blocker, pm
}
task remind_alpha_blocker2 "Reminder: Alpha Blocker Meeting (${content}${major}alpha) #2" {
depends !alpha_blocker1 {gaplength 3d}
flags pm
}
task alpha_blocker2 "Alpha Blocker Meeting (${content}${major}alpha) #2" {
depends !alpha_blocker1 {gaplength 5d}
flags releng, quality, devel, blocker, pm
}
# raise awareness one week before Alpha compose
task daily_alpha_blocker "Daily Review & Notification of Open Alpha Blocker Bugs" {
depends !alpha_blocker2 {gaplength 1d}
length 4d
flags releng, quality, devel, pm, blocker
}
task remind_alpha_blocker3 "Reminder: Alpha Blocker Meeting (${content}${major}alpha) #3" {
depends !alpha_blocker2 {gaplength 3d}
flags pm
}
task alpha_blocker3 "Alpha Blocker Meeting (${content}${major}alpha) #3" {
depends !alpha_blocker2 {gaplength 5d}
flags releng, quality, devel, pm, blocker
}
task remind_alpha_blocker4 "Reminder: Alpha Blocker Meeting (${content}${major}alpha) #4" {
depends !alpha_blocker3 {gaplength 3d}
flags pm
}
task alpha_blocker4 "Alpha Blocker Meeting (${content}${major}alpha) #4" {
depends !alpha_blocker3 {gaplength 5d}
flags releng, quality, devel, pm, blocker
}
# placeholder if slip--otherwise comment out
/*
task alpha_blocker5 "Alpha Blocker Meeting (${content}${major}alpha) #5" {
depends !alpha_blocker4 {gaplength 5d}
flags releng, quality, devel, pm, blocker
}
*/
# Feature Freeze is one week before Alpha Change Deadline
# Automatically calculated based on Alpha Change Deadline
task shadow_feature_freeze "SHADOW: Anchor Feature Freeze" {
precedes !alpha_deadline {gaplength 6d}
flags hidden
}
task feature_freeze "Feature Freeze (Testable|Complete)" {
depends !shadow_feature_freeze
flags releng, quality, pm, proto, devel, key, marketing, roadmap, fpl
}
task feature_freeze_deadline_announce "Announce Feature Freeze Reached" {
depends !feature_freeze
flags pm
}
task alpha_deadline_remind "Remind Alpha Deadline in 1 week" {
depends !feature_freeze
flags pm
}
task spins_freeze "Spins Freeze--All ${content_title} ${major} Spins Identified" {
depends !shadow_feature_freeze
flags releng, quality, pm, proto, devel, key, marketing, spins, fpl
}
task talking_points "Create Talking Points" {
depends !feature_freeze {gaplength 6d}
length 5d
flags marketing
}
task feature_profiles "Feature Profiles" {
depends !talking_points
length 20d
flags marketing
}
# Branch on the same Tuesday as Feature Freeze
task branch_rawhide "Branch Fedora ${major} from Rawhide" {
depends !shadow_feature_freeze
flags releng, devel, pm, proto, key, roadmap, fpl
}
task bugzilla_description "Reflect supported versions in Bugzilla product description" {
depends !shadow_feature_freeze
flags pm
}
task rawhide_rebase "Rebase Rawhide bugs to Fedora ${major}" {
depends !shadow_feature_freeze
flags pm
}
# Create anchor for three weeks before for Feature Submission
task shadow_feature_submit_remind_3_weeks "SHADOW: Three Weeks Before Feature Submission" {
precedes !feature_submission_deadline {gaplength 15d}
flags hidden
}
# Three weeks before Feature Submission Deadline
task feature_check_remind "Request Feature Status Updates + Remind Submit Deadline" {
depends !shadow_feature_submit_remind_3_weeks
flags devel, pm
}
task alpha_releng_tickets "File All Release Engineering Tickets for ${content_title} ${major} Alpha" {
depends !shadow_feature_submit_remind_3_weeks {gaplength 3d}
flags releng
}
task feature_submit_remind_2_weeks "Feature Submission Deadline Two Weeks away" {
depends !shadow_feature_submit_remind_3_weeks {gaplength 6d}
flags devel, pm
}
#two weeks before spins submission deadline get wiki pages in order
task spins_wiki_update "Update All Spins Wiki Pages From Previous Releases" {
depends !shadow_feature_submit_remind_3_weeks
flags spins
}
task feature_submit_remind_1_week "Feature Submission Deadline One Week away" {
depends !shadow_feature_submit_remind_3_weeks {gaplength 11d}
flags devel, pm
}
# One day before compose
task alpha_installer_build1 "Submit Installer Build for QA Compose" {
depends !feature_submit_remind_1_week {gaplength 1d}
flags devel
}
# Thursday before Feature Submission deadline
task qa_alpha_compose1 "Create Installable Images for QA testing #1" {
depends !feature_submit_remind_1_week {gaplength 2d}
flags releng
}
task alpha_rawhide_install1 "Pre-Alpha Rawhide Acceptance Test Plan #1" {
depends !qa_alpha_compose1
length 6d
flags quality
}
# Create anchor for two weeks before Feature Freeze
task shadow_feature_submission_deadline "SHADOW: Two weeks before Feature Freeze" {
precedes !feature_freeze {gaplength 10d}
flags hidden
}
task feature_submission_deadline "Feature Submission Deadline" {
depends !shadow_feature_submission_deadline
flags releng, quality, pm, proto, devel, key, roadmap, fpl
}
task feature_submission_deadline_announce "Announce Feature Submission Closed" {
depends !shadow_feature_submission_deadline
flags pm
}
task spins_submission_deadline "Custom Spins Submission Deadline" {
depends !shadow_feature_submission_deadline
flags pm, proto, key, spins, fpl
}
task warn_rawhide_rebase "Rawhide Rebase Warning to Package Maintainers" {
depends !shadow_feature_submission_deadline
flags pm
}
task ticket_rawhide_rebase "File Rawhide Rebase ticket with RHT Eng-ops" {
depends !shadow_feature_submission_deadline
flags pm
}
# One day before compose
task alpha_installer_build2 "Submit Installer Build for QA Compose" {
depends !feature_submission_deadline {gaplength 2d}
flags devel
}
task qa_alpha_compose2 "Create Installable Images for QA testing #2" {
depends !feature_submission_deadline {gaplength 3d}
flags releng
}
task alpha_rawhide_install2 "Pre-Alpha Rawhide Acceptance Test Plan #2" {
depends !qa_alpha_compose2
length 5d
flags quality
}
# One day before compose
task alpha_installer_build3 "Submit Installer Build for QA Compose" {
depends !qa_alpha_compose2 {gaplength 4d}
flags devel
}
task qa_alpha_compose3 "Create Installable Images for QA testing #3" {
depends !alpha_rawhide_install2
flags releng
}
task alpha_rawhide_install3 "Pre-Alpha Rawhide Acceptance Test Plan #3" {
depends !qa_alpha_compose3
length 5d
flags quality
}
task feature_incomplete_nag "Remind < 85% complete Feature Owners" {
depends !feature_freeze {gaplength 1d}
flags pm
}
task feature_incomplete_fesco "Deliver Incomplete Features to FESCo " {
depends !feature_freeze {gaplength 6d}
flags pm
}
# KEY ADJUSTMENT POINT
# Date of Alpha Deadline depends on length of development
task alpha_deadline "Alpha Change Deadline" {
depends !!!DevelopmentPhase.develop
flags releng, quality, pm, devel, key, roadmap, proto, blocker, spins
}
task alpha_deadline_announce "Announce Alpha Change Deadline Reached" {
depends !alpha_deadline
flags pm
}
# KEY ADJUSTMENT POINT--manually adjust if length of time before Alpha ships changes
task alpha_infrastructure_freeze "Alpha Infrastructure Change Freeze" {
depends !alpha_deadline
length 10d
flags infrastructure
}
task alpha_spins_ks "Build spin-kickstarts package from master" {
depends !alpha_deadline
flags spins
}
# Happens the same day as Feature Freeze
task orphan "Orphan Rawhide Packages" {
depends !feature_freeze
flags releng, devel
}
task finalize_alpha_wallpaper "Finalize Alpha Wallpaper" {
depends !!!PlanningPhase.wallpaper_design
flags design, pm
length 3d
}
task alpha_wallpaper_deadline "Alpha Wallpaper Deadline" {
depends !finalize_alpha_wallpaper
flags design
}
task blog_alpha_wallpaper "Blog About Alpha Wallpaper" {
depends !finalize_alpha_wallpaper
flags design
}
# must land a few days before Alpha compose by Releng
task package_alpha_wallpaper "Package Alpha Wallpaper" {
depends !finalize_alpha_wallpaper
length 2d
flags design
}
task alpha_wallpaper_feedback "Solicit Feedback on Alpha Wallpaper" {
depends !package_alpha_wallpaper
length 10d
flags design
}
# depends on nearly complete version of the wallpaper, otherwise
# you have to create the splashes twice
# work on until Beta freeze
task start_splash_screens "Create Splash Screens" {
depends !alpha_drop
length 9d
flags design
}
# for ics file
task start_splash_screens_cal "Start Splash Screens" {
depends !alpha_drop
flags design
}
# work on until Beta freeze
task finalize_splash_screens "Finalize Splash Screens" {
depends !start_splash_screens
length 4d
flags design
}
# work on until Beta freeze
task beta_wallpaper "Prepare wallpaper for Beta" {
depends !alpha_drop
length 13d
flags design
}
# send reminder on Monday before Wednesday meeting
task remind_alpha_go_not "Reminder: ${content_title} ${major} Alpha Go/No-Go Meeting" {
depends !create_alpha_compose {gaplength 2d}
flags pm
}
task alpha_go_not "${content_title} ${major} Alpha Go/No-Go Meeting (17:00 US Eastern)" {
depends !create_alpha_compose {gaplength 4d}
flags releng, quality, devel, pm, proto, blocker
}
task trans_software_rebuild1 "Remind f-dev-announce to Rebuild All Translated Packages" {
depends !feature_freeze {gaplength 5d }
flags translation
}
task software_string_freeze "Software String Freeze" {
depends !feature_freeze {gaplength 6d }
flags devel, translation, pm, proto, releng, key, roadmap
}
task announce_software_string_freeze "Announce Software String Freeze Reached" {
depends !feature_freeze {gaplength 6d }
flags pm
}
task software_translation "Software Translation"{
# KEY ADJUSTMENT POINT
# if the alpha slips, add additional time to this task (or maybe not - this may be attached to string freeze dates increasing - double check this! -robyn)
task trans_software "Software Translation Period" {
depends !!software_string_freeze
length 25d
flags translation
}
# KEY ADJUSTMENT POINT
# If the alpha slips, add additional time to 'gaplength' for this task which essentially extends the freeze
task remind_build_trans_software "Remind f-dev-announce to build F${major} collection pkgs for trans team" {
depends !!software_string_freeze {gaplength 9d}
flags translation
}
task request_review_image "Create Rel-Eng ticket for Live Image compose for Software Review UI" {
depends !remind_build_trans_software {gaplength 4d}
flags translation
}
task build_trans_software "Build F-${major} collection packages for all language translators" {
depends !request_review_image
flags releng, devel
}
task compose_review_image "Compose of Live Image of Software Review UI for Translation" {
depends !build_trans_software
flags releng
}
task trans_software_review "Review and correct software translation in built UI" {
depends !build_trans_software {gaplength 1d}
length 6d
flags translation
}
task trans_software_rebuild2 "Remind f-dev-announce to Rebuild All Translated Packages" {
depends !trans_software_review
flags translation
}
# Should land one week before the "Beta Change Deadline"--affected by "remind_build_trans_software"
# Double check after adjusting "trans_software" or length of Alpha tasks for a slip
task trans_software_deadline "Software: Translation Deadline (PO Files complete)" {
depends !trans_software_review
flags translation, roadmap, key
}
# for ical file
task start_trans_rebuild "Software: Start Rebuild all translated packages" {
depends !trans_software_deadline
flags devel
}
task trans_rebuild "Software: Rebuild all translated packages" {
depends !trans_software_deadline
length 5d
flags devel
}
} #end software_translation
# Send reminder on Monday before Thursday meeting
task alpha_meeting_reminder "Reminder: Alpha Release Readiness Meeting" {
depends !feature_freeze {gaplength 10d}
flags pm
}
task alpha_meeting "${content_title} ${major} Alpha Release Readiness Meeting" {
depends !alpha_meeting_reminder {gaplength 3d}
flags releng, pm, quality, docs, design, translation, marketing, web
}
# land on a Tuesday
task shadow_before_alpha_compose "SHADOW: 1.5 weeks before Alpha Compose" {
precedes !create_alpha_compose {gaplength 8d}
flags hidden
}
task create_alpha_tc "Create Alpha Test Compose (TC)" {
depends !shadow_before_alpha_compose
flags releng, proto
}
# test Wed to Wed
task test_alpha_tc "Test Alpha 'Test Compose'" {
depends !create_alpha_tc {gaplength 1d}
length 6d
flags quality, proto
}
task alpha_kernel_build "Submit Kernel Build for Alpha RC Compose" {
depends !alpha_deadline
flags devel
}
task alpha_installer_build "Submit Installer Build for Alpha RC Compose" {
depends !alpha_deadline {gaplength 1d}
flags devel
}
task create_alpha_compose "Compose Alpha Candidate" {
depends !alpha_deadline {gaplength 2d}
flags releng, proto
}
task test_alpha_candidate "Test Alpha Candidate" {
depends !create_alpha_compose
length 5d
flags quality, proto
}
# for ical file
task start_stage_alpha "Start Stage & Sync Alpha to Mirrors" {
depends !test_alpha_candidate
flags releng
}
task notify_mirrors_alpha "Notify Mirrors of ${content_title} ${major} Alpha" {
depends !start_stage_alpha {gaplength 1d}
flags releng
}
task stage_alpha "Stage & Sync Alpha to Mirrors" {
depends !test_alpha_candidate
length 3d
flags releng, proto
}
task alpha_export_control "Alpha Export Control Reporting" {
depends !start_stage_alpha {gaplength 1d}
flags releng, pm
}
task alpha_announce "Create Alpha Announcement (Marketing & Docs)" {
depends !alpha_meeting
length 2d
flags docs, marketing
}
task alpha_drop "Alpha Public Availability" {
depends !stage_alpha
flags releng, docs, quality, design, pm, proto, devel, key, marketing, roadmap, spins, blocker, infrastructure, fpl
}
task ambassador_start "FAmSCo heads Ambassador Wide Meetings Preparing For ${content_title} ${major}" {
depends !alpha_drop {gaplength 7d}
length 5d
flags ambassadors
}
task start_swag "FAmSCo and Regional teams call for Preparation of Media/SWAG" {
depends !alpha_drop {gaplength 7d}
flags ambassadors
}
task swag_poc "Regional Team Meetings and Select POC for Swag/Media production" {
depends !alpha_drop {gaplength 8d}
length 5d
flags ambassadors
}
task swag_funding_request "Regional Teams Submit Funding Request For Swag/Media Production" {
depends !alpha_drop {gaplength 8d}
length 5d
flags ambassadors
}
# this task was proposed by Mike McGrath and to be performed by FES
task nvr_testing "NVR Update Check testing" {
depends !stage_alpha
length 1d
flags quality
}
# KEY ADJUSTMENT POINT
task alpha_release_notes "Alpha Release Notes" {
# create for ical
task start_alpha_beats "Start Alpha Beat and Feature Page Review" {
depends !!feature_freeze {gaplength 6d}
flags docs, quality
}
task validate_beat_writers "Validate Former Beat Writers" {
depends !!feature_freeze
length 5d
flags docs
}
task recruited_beat_writers "Recruit New Beat Writers" {
depends !validate_beat_writers
length 5d
flags docs
}
task comb_alpha_beats "Comb Beats and Feature Pages for Alpha" {
depends !start_alpha_beats
length 2d
flags docs, quality
}
task notify_devel_relnotes "Notify Development About Alpha Release Notes" {
depends !!alpha_deadline
flags docs
}
# KEY ADJUSTMENT POINT
# Beta release notes depend on this task
# If alpha candidate is not ready on time add extra time for the release notes here
task prep_alpha_notes "Prepare Alpha Release Notes (1 page)" {
depends !comb_alpha_beats
length 6d
flags docs, quality
}
task post_notes "Post Alpha Release Notes One-Page" {
depends !prep_alpha_notes {gaplength 1d}
flags docs
}
} #end alpha_release_notes
# two days to create web banner
# one day for websites team to add to www.fedoraproject.org
# should be live one day before the release
task alpha_banner "Alpha Release Banner" {
precedes !alpha_drop {gaplength 3d}
task alpha_create_banner "Create Alpha Website Banner" {
length 2d
flags design
}
task alpha_publish_banner "Add Alpha Banner to Website" {
length 1d
flags web
}
}
# KEY ADJUSTMENT POINT
# Three weeks for Alpha Testing
# IF "Beta Deadline" is missed the length of this task is extended--
# in that case corresponding change needs to be made to "software_translation" task
task test_alpha "Alpha Testing" {
depends !stage_alpha
length 15d
flags quality, proto
}
task review_bookmarks "Review Firefox Bookmarks For Update" {
depends !stage_alpha
length 5d
flags marketing
}
task update_bookmarks "Update and Package Firefox Bookmarks" {
depends !review_bookmarks
length 2d
flags marketing
}
task tag_bookmarks "Tag Updated Bookmarks Package for ${content_title} ${major}" {
depends !update_bookmarks
flags marketing
}
# Explicit task to mark end of alpha
# Also permits subsequent tasks to cleanly depend on it using "precedes" (because it is zero length)
task alpha_end "End of Alpha Testing" {
depends !test_alpha
flags quality
}
task beta_marketing_notes "Marketing: Beta One Page Release Notes" {
depends !alpha_end {gaplength 5d}
length 5d
flags marketing
}
}
task beta "Beta Release" {
# KEY ADJUSTMENT POINT--if the Alpha slips, make sure the blocker meeting
# tasks continue to line up correctly
# Once the Alpha is staged, start holding Blocker meetings for the Beta
task remind_beta_blocker1 "Reminder: Beta Blocker Meeting (${content}${major}beta) #1" {
depends !!alpha.create_alpha_compose {gaplength 9d }
flags pm
}
task beta_blocker1 "Beta Blocker Meeting (${content}${major}beta) #1" {
depends !!alpha.stage_alpha {gaplength 3d }
flags quality, releng, devel, pm, blocker
}
task beta_releng_tickets "File All Release Engineering Tickets for ${content_title} ${major} Beta" {
depends !!alpha.stage_alpha {gaplength 2d }
flags releng
}
task remind_beta_blocker2 "Reminder: Beta Blocker Meeting (${content}${major}beta) #2" {
depends !beta_blocker1 {gaplength 3d}
flags pm
}
task beta_blocker2 "Beta Blocker Meeting (${content}${major}beta) #2" {
depends !beta_blocker1 {gaplength 5d}
flags releng, quality, devel, pm, blocker
}
# raise awareness one week before Beta compose
task daily_beta_blocker "Daily Review & Notification of Open Beta Blocker Bugs" {
depends !beta_blocker2 {gaplength 1d}
length 4d
flags releng, quality, devel, pm, blocker
}
task remind_beta_blocker3 "Reminder: Beta Blocker Meeting (${content}${major}beta) #3" {
depends !beta_blocker2 {gaplength 3d}
flags pm
}
task beta_blocker3 "Beta Blocker Meeting (${content}${major}beta) #3" {
depends !beta_blocker2 {gaplength 5d}
flags releng, quality, devel, pm, blocker
}
task remind_beta_blocker4 "Reminder: Beta Blocker Meeting (${content}${major}beta) #4" {
depends !beta_blocker3 {gaplength 3d}
flags pm
}
task beta_blocker4 "Beta Blocker Meeting (${content}${major}beta) #4" {
depends !beta_blocker3 {gaplength 5d}
flags releng, quality, devel, pm, blocker
}
# Create anchor one week before for Beta Deadline
task shadow_beta_deadline "SHADOW: one week before Beta Deadline" {
precedes !beta_deadline {gaplength 6d}
flags hidden
}
task remind_beta_deadline "Remind Beta Deadline in 1 week" {
depends !shadow_beta_deadline
flags pm
}
task remind_final_features "Remind Features 100% Complete in 1 week" {
depends !shadow_beta_deadline
flags pm
}
task beta_spins_ks "Build spin-kickstarts package from master" {
depends !shadow_beta_deadline
flags spins
}
task coordinate_swag_design "FAmSCo Coordinate Media/Swag/Poster artwork with Design team" {
depends !shadow_beta_deadline {gaplength 5d}
length 10d
flags ambassadors
}
# Two weeks before the public Beta Release
task beta_deadline "Beta Change Deadline" {
depends !!alpha.test_alpha
flags releng, docs, quality, pm, proto, devel, key, marketing, spins, roadmap
}
task feature_complete "Features 100% Complete Deadline" {
depends !!alpha.test_alpha
flags releng, docs, quality, pm, proto, devel, key, marketing, roadmap, fpl
}
# KEY ADJUSTMENT POINT--manually adjust if length of time before Beta ships changes
task beta_infrastructure_freeze "Beta Infrastructure Change Freeze" {
depends !!alpha.test_alpha
length 10d
flags infrastructure, releng
}
task announce_beta_deadline "Announce Beta Deadline & Feature Complete" {
depends !!alpha.test_alpha
flags pm
}
task final_feature_fesco "Deliver features < 100% to FESCo" {
depends !beta_deadline {gaplength 1d}
flags pm
}
task brief_ambassadors "Brief Ambassadors on upcoming release" {
depends !beta_deadline {gaplength 5d}
length 5d
flags marketing
}
# The Release Slogan is created by the Marketing team based on
# the initial artwork theme. The Design Team needs to know
# the slogan to create the release banners
# prepare 6 weeks before GA (2 weeks of work)
# go live 1 month before GA
# KEY ADJUSTMENT POINT
task create_countdown "Create Count Down Graphic" {
depends !beta_deadline
length 10d
flags design
}
task publish_countdown "Publish Count Down Graphic" {
depends !create_countdown
length 1d
flags web
}
task beta_release_notes "Beta Release Notes" {
task unclaimed_beats "Write Unclaimed Wiki Beats" {
depends !!!alpha.alpha_drop
length 6d
flags docs
}
task port_wiki_publican "Port Wiki to Publican" {
depends !unclaimed_beats {gaplength 1d}
length 3d
flags docs
}
task remind_trans_beta_notes "Remind Translation: Beta Rel Notes POT Coming" {
depends !unclaimed_beats
flags docs
}
task start_release_notes_pot1 "Start nightly POT files all fed-rel-notes.rpm content" {
depends !port_wiki_publican {gaplength 1d}
flags docs
}
task release_notes_pot1 "Generate nightly POT files all fed-rel-notes.rpm content" {
depends !port_wiki_publican {gaplength 1d}
length 13d
flags docs
}
task remind_devel_beta_notes"Remind announce-list & f-devel-announce: Wiki Freeze" {
depends !unclaimed_beats {gaplength 1d}
flags docs
}
task beta_wiki_freeze "Wiki Freeze: Beta Release Notes" {
depends !remind_devel_beta_notes {gaplength 2d}
flags docs
}
task trans_release_notes "Translate Beta Release Notes" {
depends !port_wiki_publican {gaplength 1d}
length 14d
flags translation
}
# KEY ADJUSTMENT POINT
task build_trans_review "Ongoing build translation review htmls" {
depends !beta_wiki_freeze
length 5d
flags docs
}
# KEY ADJUSTMENT POINT
task trans_review_beta "Review and correct Beta Release Notes (daily buids html)" {
depends !beta_wiki_freeze
length 5d
flags translation
}
task trans_release_notes_deadline "Translation Deadline: Beta Release Notes (PO Files complete)" {
depends !trans_review_beta
flags translation, docs
}
task build_beta_relnotes "Build f-r-n.rpm and Push to updates-candidate" {
depends !trans_release_notes_deadline
length 2d
flags docs, translation
}
task final_release_notes_reminder "Reminder: Send Project Wide-Final Release Notes Deadlines" {
depends !!beta_deadline {gaplength 7d}
flags docs
}
# one day before release which is 2D after meeting
task web_notes "Build and Post Beta release-notes to docs.fedoraproject.org" {
depends !!beta_meeting {gaplength 2d}
flags docs
}
# one day before release which is 2D after meeting
task tech_web_notes "Build and Post Fedora Technical Notes to docs.fedoraproject.org" {
depends !!beta_meeting {gaplength 2d}
flags docs
}
} # end beta_release_notes
task splash_deadline "Deadline: Beta Splash Screens" {
depends !!alpha.finalize_splash_screens
flags design
}
task package_final_splash "Package: Beta Splash Screens" {
depends !!alpha.finalize_splash_screens
length 2d
flags design
}
task package_beta_wallpaper "Package: Beta Wallpaper"{
depends !!alpha.beta_wallpaper
length 2d
flags design
}
task package_supplemental_wallpaper "Package: Supplemental Wallpaper"{
depends !!alpha.beta_wallpaper
flags design
}
task beta_meeting_announce "Announce: Beta Release Readiness Meeting" {
flags pm
}
# KEY ADJUSTMENT POINT if Beta Deadline changes
task beta_meeting_reminder "Reminder: Beta Release Readiness Meeting" {
depends !beta_deadline {gaplength 4d}
flags pm
}
task beta_meeting "${content_title} ${major} Beta Release Readiness Meeting" {
depends !beta_meeting_reminder {gaplength 3d}
flags releng, pm, quality, docs, design, translation, marketing, web
}
task beta_announce "Create Beta Announcement (Docs & Marketing)" {
depends !beta_meeting
length 2d
flags docs, marketing
}
# placeholder if slip
# task beta_blocker4 "Beta Blocker Day (${content}${major}beta) #4" {
# depends !!beta_blocker3 {gaplength 5d}
# flags releng, quality, devel, pm, blocker
# }
task shadow_before_beta_compose "SHADOW: 1.5 weeks before Beta Compose" {
precedes !create_beta_compose {gaplength 9d} # with 'precedes', gaplength pushes date backwards
flags hidden
}
task beta_installer_build1 "Submit Installer Build for Beta TC Compose" {
depends !shadow_before_beta_compose
flags devel
}
task create_beta_tc "Create Beta Test Compose (TC)" {
depends !shadow_before_beta_compose {gaplength 2d}
flags releng, proto
}
task test_beta_tc "Test Beta 'Test Compose'" {
depends !create_beta_tc
length 6d
flags quality, proto
}
task beta_rawhide_install "Pre-Beta Acceptance Test Plan" {
precedes !create_beta_tc
length 5d
flags quality
}
task remind_beta_go_not "Reminder: ${content_title} ${major} Beta Go/No-Go Meeting" {
depends !create_beta_compose {gaplength 2d}
flags pm
}
task beta_go_not "${content_title} ${major} Beta Go/No-Go Meeting (17:00 US Eastern)" {
depends !create_beta_compose {gaplength 4d}
flags releng, quality, devel, pm, proto, blocker
}
task beta_kernel_build "Submit Kernel Build for Beta RC Compose" {
depends !beta_deadline
flags devel
}
task beta_installer_build "Submit Installer Build for Beta RC Compose" {
depends !beta_deadline {gaplength 1d}
flags devel
}
# KEY ADJUSTMENT POINT if Beta release date slips--add more time to this task
task create_beta_compose "Compose Beta Candidate" {
depends !beta_deadline {gaplength 2d}
flags releng, proto
}
task call_for_events "FAmSCo and Regional Teams Call for Release Events" {
depends !beta_deadline {gaplength 12d}
flags ambassadors
}
task logistics_budget "Regional Teams Plan Regional Logistics for Release Events & File Budget Requests" {
depends !call_for_events
length 10d
flags ambassadors
}
task test_beta2 "Test Beta Candidate" {
depends !create_beta_compose
length 5d
flags quality, proto
}
task start_stage_beta "Start Stage & Sync Beta to Mirrors" {
depends !test_beta2
flags releng
}
task notify_mirrors_beta "Notify Mirrors of ${content_title} ${major} Beta" {
depends !start_stage_beta {gaplength 1d}
flags releng
}
task stage_beta "Stage & Sync Beta to Mirrors" {
depends !test_beta2
length 3d
flags releng, proto
}
task beta_export_control "Beta Export Control Reporting" {
depends !start_stage_beta {gaplength 1d}
flags releng, pm
}
# two days to create web banner
# one day for websites team to add to www.fedoraproject.org
# should be live one day before the release
task beta_banner "Beta Release Banner" {
precedes !beta_drop {gaplength 3d}
task beta_create_banner "Create Beta Website Banner" {
length 2d
flags design
}
task beta_publish_banner "Add Beta Banner to Website" {
length 1d
flags web
}
}
task shadow_before_beta_drop "SHADOW: One Day before Public Beta release" {
precedes !beta_drop {gaplength 2d}
flags hidden
}
# Five weeks prior to GA
task beta_drop "Beta Release Public Availability" {
depends !stage_beta
flags docs, releng, quality, pm, translation, proto, design, devel, key, marketing, roadmap, blocker, spins, infrastructure, fpl
}
task event_deadline "Release Event Submission Deadline" {
depends !logistics_budget {gaplength 1d}
flags ambassadors
}
task budget_allocations "FAmSCo Review Budget Allocations" {
depends !event_deadline
flags ambassadors
}
task irc_sessions "FAmSCo Regional IRC town halls" {
depends !beta_drop {gaplength 8d}
length 10d
flags ambassadors
}
# Three weeks of public testing
# Ends on a Monday and is followed by Final Release Deadline
task beta_test "Beta Testing" {
depends !stage_beta
length 14d
flags quality, proto
}
task websites_trans_reminder "Reminder to f-websites-list about POT/PO dates in 7 days" {
depends !beta_drop
flags translation, web
}
# two weeks to create
# should be completely done and ready for hand off to Ambassadors two weeks before GA
# Ambassadors should have made prior arrangements to flip artwork over to media producer
# at this time.
task media "Create DVD/CD label and sleeve artwork" {
# not a "great" place to anchor to as it could move
# needs to start four weeks before GA
depends !beta_drop
length 10d
flags design
}
task rc_rawhide_install "Pre-RC Acceptance Test Plan" {
depends !stage_beta {gaplength 7d}
length 4d
flags quality
}
task testmile "End of Beta Testing" {
depends !beta_test
flags quality
}
}
} # E N D of TestingPhase
task LaunchPhase "Launch Phase" {
# four weeks before GA, ambassadors create release posters
# two weeks before GA to art team does final polish to posters
# posters are ready on release day
task release_posters "Release Party Posters" {
depends !!TestingPhase.beta.beta_drop
task create_posters "FAmSCo with Design Team Create Release Party Posters" {
length 10d
flags ambassadors
}
task polish_poster "Polish/Finalize Release Party Posters" {
depends !create_posters
length 9d
flags design
}
}
task screenshots "Update and freeze the screenshots page" {
depends !!TestingPhase.beta.stage_beta {gaplength 5d}
length 5d
flags marketing
}
task final_screenshots "Marketing: Final Screen Shots" {
depends !screenshots
length 5d
flags marketing
}
task final_marketing_notes "Marketing: Final One Page Release Notes" {
depends !screenshots
length 5d
flags marketing
}
task briefings "Brief news distribution network" {
depends !screenshots
length 5d
flags marketing
}
task monitor "Monitor news sites to provide corrections & info" {
depends !screenshots
length 29d
flags marketing
}
task rc "Release Candidate" {
task final_releng_tickets "File All Release Engineering Tickets for ${content_title} ${major} GA" {
depends !!!TestingPhase.beta.stage_beta {gaplength 2d }
flags releng
}
task remind_ga_blocker1 "Reminder: Final Blocker Meeting (${content}${major}blocker) #1" {
depends !!!TestingPhase.beta.create_beta_compose {gaplength 4d}
flags pm
}
task ga_blocker1 "Final Blocker Meeting (${content}${major}blocker) #1" {
depends !!!TestingPhase.beta.start_stage_beta {gaplength 1d}
flags releng, quality, devel, pm, blocker
}
task remind_ga_blocker2 "Reminder: Final Blocker Meeting (${content}${major}blocker) #2" {
depends !ga_blocker1 {gaplength 3d}
flags pm
}
task ga_blocker2 "Final Blocker Meeting (${content}${major}blocker) #2" {
depends !ga_blocker1 {gaplength 5d}
flags releng, quality, devel, pm, blocker
}
task remind_ga_blocker3 "Reminder: Final Blocker Meeting (${content}${major}blocker) #3" {
depends !ga_blocker2 {gaplength 3d}
flags pm
}
task ga_blocker3 "Final Blocker Meeting (${content}${major}blocker) #3" {
depends !ga_blocker2 {gaplength 5d}
flags releng, quality, devel, pm, blocker
}
# two days before Final Deadline
task shadow_before_final_deadline "SHADOW: one day before Final Deadline" {
precedes !final_change_deadline {gaplength 2d}
flags hidden
}
task kernel_debug "Disable Kernel debug and submit new Kernel build for RC" {
depends !shadow_before_final_deadline
flags devel
}
task final_change_deadline "Final Change Deadline" {
depends !!!TestingPhase.beta.beta_test
flags releng, devel, proto, pm, key, spins
}
task check_swag "FAmSCo and Regional Teams Meet to Address Unresolved Events/Media/Swag Issues" {
depends !final_change_deadline {gaplength 1d}
flags ambassadors
}
# one day before Final Deadline
task final_wallpaper "Package Final Wallpaper" {
depends !shadow_before_final_deadline
flags design
}
# one day before Final Deadline
task final_splash "Package Final Splash Screens" {
depends !shadow_before_final_deadline
flags design
}
task announce_final_change_deadline "Announce Final Freeze & Implications" {
depends !final_change_deadline
flags pm
}
# ADJUST FOR NEW RELEASE--EOL Version
task eol_warning "File RHT Eng-ops ticket for Fedora 15 EOL Bugzilla warning" {
depends !final_change_deadline
flags pm
}
# KEY ADJUSTMENT POINT--manually adjust if length of time before Final release ships changes
task final_infrastructure_freeze "Final Infrastructure Change Freeze" {
depends !!!TestingPhase.beta.beta_test {gaplength 1d}
length 10d
flags infrastructure, releng
}
task remind_ga_blocker4 "Reminder: Final Blocker Meeting (${content}${major}blocker) #4" {
depends !ga_blocker3 {gaplength 3d}
flags pm
}
task ga_blocker4 "Final Blocker Meeting (${content}${major}blocker) #4" {
depends !ga_blocker3 {gaplength 5d}
flags releng, quality, devel, pm, blocker
}
# raise awareness one week before final compose
task daily_ga_blocker "Daily Review & Notification of Open Final Blocker Bugs" {
depends !ga_blocker3 {gaplength 1d}
length 4d
flags releng, quality, devel, pm, blocker
}
task ga_blocker5 "Final Blocker Meeting (${content}${major}blocker)--Blocks RC Compose" {
depends !ga_blocker4 {gaplength 1d}
flags releng, quality, devel, pm, blocker
}
task ga_release_notes "Final Release Notes" {
# One day before public beta release
task final_release_note_wiki_reminder "Reminder to Development: Wiki Freeze in 7 days" {
depends !!!!TestingPhase.beta.shadow_before_beta_drop
flags docs
}
task prep_ga_notes "Prepare GA Release Notes" {
depends !!!!TestingPhase.beta.beta_drop
flags docs, quality
}
task ga_release_notes_freeze "String Freeze: GA Release Notes" {
depends !prep_ga_notes {gaplength 4d}
flags docs
}
task wiki_ga_port "Port diff wiki content to Publican" {
depends !ga_release_notes_freeze
length 5d
flags docs
}
task remind_trans_ga_notes "Remind Translation: RPM Freeze (no more POTs) in 5 days" {
depends !ga_release_notes_freeze {gaplength 2d}
flags docs
}
# KEY ADJUSTMENT POINT--if length of Beta changes this task length needs to change too
task ga_pot_trans "Translate Final Release Notes (POT to PO)" {
depends !!!!TestingPhase.beta.beta_release_notes.trans_release_notes_deadline {gaplength 1d}
length 24d
flags translation
}
task ga_release_notes_pot "Generate GA Release Notes POT files for Translation" {
depends !wiki_ga_port
flags docs
}
task build_trans_review_final "Build GA release note htmls for Translation" {
depends !ga_release_notes_pot {gaplength 1d}
length 4d
flags docs
}
task build_ga_trans_review "Review and correct GA Release Notes (daily builds html)" {
depends !ga_release_notes_pot {gaplength 1d}
length 4d
flags docs, translation
}
task remind_ga_trans_deadline "Remind Translators of GA Release Notes Deadline in 4 days" {
depends !ga_release_notes_pot {gaplength 3d}
flags docs
}
task ga_release_notes_po "Translation Deadline: GA rel-notes (PO Files complete)" {
depends !ga_pot_trans
flags translation
}
task ga_release_notes_rpm "Build fedora-release-notes.rpm" {
depends !ga_release_notes_po
length 2d
flags docs
}
} #end final release notes
# Three banners are created for the GA release (based on the Slogan from Marketing)
# 1) large banner--fedoraproject.org front page
# 2) "the release is out, go get it"--fedoraproject.org front page
# 3) release name on start.fedoraproject.org
# banners take one week to complete
# banners should be completed one week before GA
# banners are translated the week up until GA
# translated during the week up until GA
task ga_create_banners "Create Final Release Banners" {
depends !!!TestingPhase.beta.testmile
length 9d
flags design
}
# Start one day before Final Change Deadline
task create_ga_announce "Create GA Announcement (Docs & Marketing)" {
depends !!!LaunchPhase.rc.shadow_before_final_deadline
length 7d
flags docs, marketing
}
task translate_ga_announce "GA Announcement available for translation (optional)" {
depends !create_ga_announce
length 5d
flags translation
}
task ga_publish_banners "Add Final Release Banners to Website" {
depends !ga_create_banners
length 1d
flags web
}
# web properties need to be updated and translated
# Tasks start at time Beta Release goes out
# http://fedoraproject.org/en/index
# http://fedoraproject.org/en/get-fedora
# http://fedoraproject.org/en/join-fedora
# http://fedoraproject.org/en/get-help
task web_content_update "Update Website Content" {
depends !!!TestingPhase.beta.beta_drop
length 5d
flags web
}
task web_freeze "Website String Freeze" {
depends !web_content_update
flags web
}
task web_create_pot "Create Website POT Files" {
depends !web_freeze
length 1d
flags web
}
task trans_web "Translation Period for Website (POT to PO)" {
depends !web_create_pot
length 9d
flags translation
}
task review_trans_web "Review and correct Website translations" {
depends !trans_web
length 4d
flags translation, web
}
task finish_trans_web "Translation Deadline: Websites (POs done)" {
depends !review_trans_web
flags translation
}
task publish_trans_web "Publish Translations on Website (fedoraproject.org)" {
depends !review_trans_web
length 1d
flags web
}
task final_meeting_reminder "Reminder: Final Release Readiness Meeting" {
depends !!!TestingPhase.beta.beta_test {gaplength 5d}
flags pm
}
task ga_meeting "${content_title} ${major} Final Release Readiness Meeting" {
depends !final_meeting_reminder {gaplength 3d}
flags releng, pm, quality, docs, design, marketing, translation, web
}
task shadow_before_final_compose "SHADOW: one week before RC Compose" {
precedes !start_final_compose {gaplength 8d}
flags hidden
}
task final_installer_build1 "Submit Installer Build for Final TC Compose" {
depends !shadow_before_final_compose
flags devel
}
task create_final_tc "Create 'Final' Test Compose (TC)" {
depends !shadow_before_final_compose {gaplength 2d}
flags releng, proto
}
task test_final_tc "Test 'Final' Test Compose (TC)" {
depends !create_final_tc
length 4d
flags quality, proto
}
task final_installer_build "Submit Installer Build for Final RC Compose" {
depends !final_change_deadline
flags devel
}
task start_final_compose "Compose 'Final' RC: DVD, Live, Spins" {
depends !final_change_deadline {gaplength 1d}
length 1d
flags releng, key, roadmap, proto
}
task early_iso "Regional Teams Obtain Final Release ISOs from Release Engineering for duplication" {
depends !test_final {gaplength 2d}
length 3d
flags ambassadors
}
task regional_marketing "Regional Coordination with Marketing for Release Events" {
depends !test_final {gaplength 2d}
length 5d
flags ambassadors
}
task deliver_final "Deliver RC to QA for Testing" {
depends !start_final_compose
flags releng, proto
}
task test_final "Test 'Final' RC" {
depends !deliver_final
length 4d
flags quality
}
# for ics file
task start_stage_final "Start Stage & Sync RC to Mirrors" {
depends !test_final {gaplength 2d}
flags releng
}
task notify_mirrors_final "Notify Mirrors of ${content_title} ${major} Final" {
depends !start_stage_final {gaplength 1d}
flags releng
}
task stage_final "Stage & Sync RC to Mirrors" {
depends !test_final {gaplength 2d}
length 3d
flags releng, proto
}
task package_spins_ks "Branch spin-kickstarts and build package from new branch" {
depends !create_final_tc
flags spins
}
task freeze_spins_ks "Spins kickstart package Freeze" {
depends !create_final_tc
flags spins
}
task enable_updates "Enable ${content_title} ${major} Updates" {
depends !!!TestingPhase.beta.beta_test {gaplength 2d}
flags releng
}
task remind_final_go_not "Reminder: ${content_title} ${major} Final Go/No-Go Meeting" {
depends !start_final_compose {gaplength 1d}
flags pm
}
# Hold on Tuesday instead of Wednesday (Alpha and Beta)--this provides a little cushion
# if something goes wrong. Mirrors do not have to start sync until Thursday
task final_go_not "${content_title} ${major} Final Go/No-Go Meeting (17:00 US Eastern)" {
depends !start_final_compose {gaplength 4d}
flags releng, quality, docs, pm, proto, blocker
}
task final_export_control "Final Export Control Reporting" {
depends !start_stage_final {gaplength 1d}
flags releng, pm
}
# Zero-day tasks should start two Fridays before GA and finish the day before GA
task zero_day_relnotes "Zero Day Release Notes" {
task shadow_zero_day "SHADOW: Seven work week days before GA" {
precedes !!!final {gaplength 7d}
flags hidden
}
task zero_day_web "0-Day rel-notes update docs.fp.org" {
depends !shadow_zero_day
length 6d
flags docs
}
task zero_day_rpm "0-Day rel-notes build updated rpm" {
depends !shadow_zero_day
length 6d
flags docs
}
task zero_day_pot "0-Day rel-notes generate POT" {
depends !shadow_zero_day
length 6d
flags docs
}
task zero_day_trans "Translate 0-Day Release Notes" {
depends !shadow_zero_day
length 6d
flags translation
}
task zero_day_deadline "Translation Deadline: 0-Day (PO Files complete)" {
depends !zero_day_trans
flags translation
}
task web_post "Add translated zero-day updates to docs.fp.org" {
depends !zero_day_trans
flags docs
}
task post_tech_notes "Update and post Fedora Technical Notes to docs.fedoraproject.org" {
depends !!!final
flags docs
}
# Monday after Tuesday GA
task push_updates_rpm "Push updated rel-notes RPMs to Updates repo" {
depends !!!final {gaplength 4d}
flags docs
}
} # zero_day_relnotes
} # end of rc task
task bugzilla_description "Reflect supported versions in Bugzilla product description" {
depends !rc.stage_final
flags pm
}
task final "Final (GA) Release" {
depends !rc.stage_final
flags quality, releng, docs, design, pm, translation, proto, devel, key, marketing, roadmap, spins, infrastructure, fpl
}
# ADJUST FOR NEW RELEASE--EOL Version
task remind_eol "Send Email Reminder About Fedora 16 EOL Activities" {
depends !final {gaplength 2d}
flags releng, pm, devel
}
task event_reports "Hold Release Events and Publish Event Reports" {
depends !final
length 23d
flags ambassadors
}
task spins_ga_ks "Build new spin-kickstarts package for updates (if necessary)" {
depends !rc.stage_final
flags spins
}
task marketing_post "Marketing Retrospective" {
depends !final
length 10d
flags marketing
}
}
# Starting in Fedora 13, the docs group wanted the Guides work to span almost
# the entire release cycle--they don't fit nicely into different phases.
# So we put them all here in their own block.
# Run from Start until one week before GA
task all_guides "${content_title} ${major} Guides" {
# Run from Start until "Branch Guides"
task continue_guides_trans "Continue translation of guides in branch of previous release " {
length 70d
flags translation
}
task test_branch_guides "Test master branches of guides against Alpha and correct" {
depends !!TestingPhase.alpha.stage_alpha
length 10d
flags docs
}
task branch_guides "Branch Guides" {
depends !test_branch_guides
flags docs
}
task guides_pot "Create POT files for All Guides" {
depends !branch_guides
flags docs
}
task notify_trans "Notify trans that new Guide POT files available " {
depends !guides_pot
flags docs
}
task trans_all_guides "Translate All Guides (POT to PO)" {
depends !guides_pot
flags docs
}
task publish_draft "Publish draft guides" {
depends !branch_guides
flags docs
}
task announce_publish_draft "Notify announce-list and f-devel-list draft guides available" {
depends !publish_draft
flags docs
}
# ADJUST FOR NEW RELEASE--make sure this task lands one day before GA
task guides_trans "Translate All Guides (POT to PO)" {
depends !guides_pot
length 39d
flags translation
}
task remind_trans_pot "Reminder to Trans that new POT files are coming for all guides" {
depends !!TestingPhase.alpha.stage_alpha {gaplength 8d}
flags docs
}
# Wednesday, one week after Beta Change Deadline
task srpm_review "Remind new guide owners SRPM package review" {
depends !!TestingPhase.beta.beta_deadline {gaplength 6d}
flags docs
}
task shadow_before_beta_deadline "SHADOW: for Friday before Beta deadline" {
precedes !!TestingPhase.beta.beta_deadline {gaplength 1d}
flags hidden
}
# Friday before Final Change Deadline
task remind_trans "Reminder to Trans that Final Guides POT files are coming" {
depends !shadow_before_beta_deadline
flags docs
}
task guides_string_freeze "String Freeze All Guides" {
depends !!LaunchPhase.rc.final_change_deadline
flags docs
}
task generate_final_pot "Generate final POT files for Guides" {
depends !guides_string_freeze
flags docs
}
task notify_trans_final "Notify Trans of Final Guides POT availability" {
depends !guides_string_freeze
flags docs
}
# Monday to Friday, two weeks before GA
task build_daily "Daily builds of Final guides for Translation" {
length 9d
depends !!LaunchPhase.rc.final_change_deadline
flags docs
}
# Monday to Friday, two weeks before GA
task review_daily "Review and correct Final Translated Guides (daily builds html)" {
depends !!LaunchPhase.rc.final_change_deadline
length 9d
flags translation
}
# Friday before GA
task shadow_guides_trans_deadline "SHADOW: Translation Deadline: All Final Guides" {
precedes !!LaunchPhase.final {gaplength 2d}
flags hidden
}
# zero duration tasks (milestones/deadlines) need a shadow precedes task so they report correctly
# Also needed for ICS files which only report milestones
task guides_trans_deadline "Translation Deadline: All Final Guides" {
depends !shadow_guides_trans_deadline
flags translation
}
task test_guides_beta "Test guides against Beta and correct" {
depends !!TestingPhase.beta.beta_drop
length 4d
flags docs
}
task refresh_pot "Refresh POT files for all guides against Beta" {
depends !test_guides_beta
flags docs
}
task notify_trans_refresh "Notify trans that POT files updated against Beta" {
depends !refresh_pot
flags docs
}
task republish_draft "Republish draft guides for Beta" {
depends !test_guides_beta
flags docs
}
task notify_revised_draft "Notify announce-list and f-devel-list revised draft guides available" {
depends !republish_draft
flags docs
}
# Friday before GA until the day before GA
task guides_final_build "Final Build All Guides: All Languages" {
depends !srpm_review
length 3d
flags docs
}
# Day before GA
task shadow_publish_guides "SHADOW: Publish all guides to docs.fp.o (html,html-single,pdf)" {
precedes !!LaunchPhase.final {gaplength 2d}
flags hidden
}
task publish_guides "Publish all guides to docs.fp.o (html,html-single,pdf)" {
depends !shadow_publish_guides
flags docs
}
} # end of "all_guides"
# Elections http://fedoraproject.org/wiki/Elections
# Board & FESCo are reelected in every release
# FAmSCo Elections are held once a year near the Halloween release
# ADJUST FOR NEW RELEASE
task elections "${content_title} ${next_major} Election Coordination" {
# manually set start date that is five weeks before GA date (on a Tuesday)
# this is cleaner than using 'precedes'
# use 'duration' to make it easier for some tasks to land on weekends
start 2013-09-24
flags elections, fpl, pm
# Don't forget to do this! Or else bad things happen.
task remind "Remind advisory-board list of upcoming election schedule" {
}
task solicit "Solicit volunteers for questionnaire and town halls" {
depends !remind
duration 7d
}
task wiki_update "Update wiki page https://fedoraproject.org/wiki/Elections with required information" {
depends !solicit
}
task advertise_elections "Advertise elections schedule and pages" {
depends !solicit
}
task announce_nominations "FPL/designee announces opening of nominations" {
depends !solicit {gapduration 25d}
}
task open_questions "Questionnaire wrangler announces opening for questions"{
depends !announce_nominations
}
task collect_questions "Collect question on the wiki"{
depends !announce_nominations
duration 8d
}
task collect_answers "Candidates write questionnaire answers" {
depends !collect_questions
duration 7d
}
task announce_town "Town hall wrangler announces schedule for town hall meetings" {
depends !announce_nominations
}
task question_deadline "Questionnaire answers due from candidates" {
depends !collect_answers
}
# five days before GA
task present_answers "Wrangler presents questionnaire answers" {
depends !collect_answers {gapduration 1d}
duration 2d
}
task post_questions "All answers posted to questionnaire page, advertise to voters" {
depends !present_answers
}
task town_hall "Town hall period" {
depends !post_questions {gapduration 1d}
duration 6d
}
task voting_application "Finalize Voting Application" {
duration 1d
depends !town_hall
}
task voting_start "Voting Begins" {
depends !voting_application
}
task voting "Voting for general elections" {
depends !voting_application
duration 6d
}
task voting_end "Voting Ends" {
depends !voting
}
task announce_results "Announce Results" {
depends !voting_end {gapduration 1d}
}
} # end elections
# The release naming process for the next release should end three weeks prior
# to the end of the current release
# It is easiest to start this task by hard coding the start date to be 6 weeks before GA
# 2010-09-14
# 1 week -- collect names
# 1 week --fedora board reviews names
# 2 weeks -- names reviewed by RHT legal
# 1 week -- community vote on names
# ADJUST FOR NEW RELEASE
task naming "Name the ${content_title} ${next_major} Release" {
start 2013-09-17 # manually set this date
flags pm, fpl
task gather "Collect ${content_title} ${next_major} Names on Wiki" {
length 5.5d
}
task board "Board Review of Proposed ${content_title} ${next_major} Names" {
depends !gather
length 3d
}
task legal "Legal Review" {
depends !board
length 5d
}
task vote "Voting" {
depends !legal
length 4d
}
task announce_name "${content_title} ${next_major} Release Name Announced" {
depends !vote {gapduration 1d}
flags design, pm
}
} # end release naming
task pr "Public Relations" {
task video "Creative team videos" {
flags fpl, pr
task video_schedule "Meet w/Creative to schedule videos" {
precedes !video1.review_spotlight1_video {gaplength 25d}
length 5d
}
task video1 "Make spotlight video #1" {
task review_spotlight1_video "Review video #1" {
precedes !release_spotlight1_video
length 15d
}
task release_spotlight1_video "Publish spotlight video #1" {
depends !!!spotlight_feature_blogs.spotlight_feature1.spotlight_feature1_drop
}
}
task video2 "Make spotlight video #2" {
task review_spotlight2_video "Review video #2" {
precedes !release_spotlight2_video
length 15d
}
task release_spotlight2_video "Publish spotlight video #2" {
depends !!!spotlight_feature_blogs.spotlight_feature3.spotlight_feature3_drop
}
}
task release_video "Make release video" {
task review_release_video "Review release video" {
precedes !release_video
length 20d
}
task release_video "Publish release video" {
depends !!!!LaunchPhase.final
}
}
} #end video
task beta_release_blog "Beta press blog entry" {
flags fpl, pr
/**
* By building the final task to be a 0-duration event
* (milestone), depending on another given task date like a
* release date, and having each other task below precede the
* one following, these tasks should auto-adjust to fall on a
* given date.
*/
task beta_release_blog_draft "Start drafting Beta blog" {
precedes !beta_release_blog_legal
length 10d
}
task beta_release_blog_legal "Red Hat PR send Beta blog to Legal" {
precedes !beta_release_blog_intl
length 5d
}
task beta_release_blog_intl "Red Hat PR send Beta blog to intl-pr list" {
precedes !beta_release_blog_drop
length 6d
}
task beta_release_blog_drop "Red Hat PR publish and send Beta blog to media contacts" {
depends !!!TestingPhase.beta.beta_drop
}
}
task spotlight_feature_blogs "Spotlight feature press blogs" {
task spotlight_feature1 "Spotlight feature #1" {
task spotlight_feature1_draft "Draft spotlight #1 blog entry" {
precedes !spotlight_feature1_legal
length 5d
flags fpl, pr
}
task spotlight_feature1_legal "Red Hat PR send spotlight #1 blog entry draft to legal" {
precedes !spotlight_feature1_drop
length 5d
flags fpl, pr
}
task shadow_spotlight_feature1 "SHADOW: Three weeks until GA" {
precedes !!!!LaunchPhase.final { gaplength 16d }
length 1d
flags hidden
}
task spotlight_feature1_drop "Red Hat PR publish spotlight #1 blog entry" {
depends !shadow_spotlight_feature1
flags fpl, pr
}
}
task spotlight_feature2 "Spotlight feature #2" {
task spotlight_feature2_draft "Draft spotlight #2 blog entry" {
precedes !spotlight_feature2_legal
length 5d
flags fpl, pr
}
task spotlight_feature2_legal "Red Hat PR send spotlight #2 blog entry draft to legal" {
precedes !spotlight_feature2_drop
length 5d
flags fpl, pr
}
task spotlight_feature2_drop "Red Hat PR publish spotlight #2 blog entry" {
depends !shadow_spotlight_feature2
flags fpl, pr
}
task shadow_spotlight_feature2 "SHADOW: Two weeks until GA" {
precedes !!!!LaunchPhase.final { gaplength 11d }
length 1d
flags hidden
}
}
task spotlight_feature3 "Spotlight feature #3" {
task spotlight_feature3_draft "Draft spotlight #3 blog entry" {
precedes !spotlight_feature3_legal
length 5d
flags fpl, pr
}
task spotlight_feature3_legal "Red Hat PR send spotlight #3 blog entry draft to legal" {
precedes !spotlight_feature3_drop
length 5d
flags fpl, pr
}
task spotlight_feature3_drop "Red Hat PR publish spotlight #3 blog entry" {
depends !shadow_spotlight_feature3
flags fpl, pr
}
task shadow_spotlight_feature3 "SHADOW: One week until GA" {
precedes !!!!LaunchPhase.final { gaplength 6d }
duration 1d
flags hidden
}
}
}
task usb_keys_prebriefs "USB Keys and media pre-briefs" {
flags fpl, pr
task buy_usb_keys "Purchase USB Keys" {
precedes !prepare_usb_keys
length 5d
}
task assess_press_kit "Check LiveUSB press review sheet for readiness" {
precedes !update_press_one_sheet
length 5d
}
task update_press_one_sheet "Update LiveUSB press review sheet" {
precedes !send_usb_keys
length 5d
}
task prepare_usb_keys "Prep USB keys with pre-release" {
precedes !send_usb_keys
length 5d
}
task send_usb_keys "Send USB keys to Red Hat PR for distribution" {
precedes !media_prebriefs {gaplength 10d}
length 3d
}
task distribute_usb_keys "Red Hat PR distribute USB keys to media contacts" {
precedes !media_prebriefs {gaplength 7d}
length 5d
}
task media_prebriefs "Hold media prebrief interviews" {
precedes !!!LaunchPhase.final
length 6d
}
}
task redhat_com_update "Update Red Hat web site" {
flags fpl, pr
task web_graphics_discuss "Schedule meeting with Red Hat web team to plan launch" {
length 5d
precedes !web_promo_to_brand
}
task web_promo_to_brand "Send web promo ideas to Brand" {
length 5d
precedes !web_copy_review
}
task web_copy_review "Review and update www.redhat.com/Fedora copy" {
length 5d
precedes !web_copy_send_update
}
task web_copy_send_update "Send updated copy to Web team" {
precedes !rh_web_goes_live { gaplength 11d }
length 5d
}
task rh_web_goes_live "Red Hat website changes go live" {
depends !!!LaunchPhase.final
}
}
task ga_press_release "GA press release" {
flags fpl, pr
task ga_press_release_draft "Start drafting GA press release" {
length 10d
precedes !ga_press_release_legal
}
task ga_press_release_legal "Red Hat PR send GA press release to Legal" {
length 5d
precedes !ga_press_release_intl
}
task ga_press_release_intl "Red Hat PR send GA press release to intl-pr list" {
length 6d
precedes !ga_press_release_drop
}
task ga_press_release_drop "Red Hat PR publish and send GA press release to media contacts" {
depends !!!LaunchPhase.final
}
}
task ceo_blog "CEO press blog entry" {
flags fpl, pr
task ceo_prepare_final_rc "Prepare a final RC on USB for CEO" {
precedes !ceo_send_final_rc
length 2d
}
task ceo_send_final_rc "Send final RC USB key to CEO" {
precedes !ceo_solicit_feedback
length 2d
}
task ceo_solicit_feedback "Solicit CEO feedback on pre-release" {
precedes !ceo_blog_draft
length 4d
}
task ceo_blog_draft "Draft CEO blog" {
precedes !ceo_blog_legal
length 3d
}
task ceo_blog_legal "Red Hat PR send CEO blog to Legal" {
precedes !ceo_blog_drop
length 3d
}
task ceo_blog_drop "Red Hat PR publish and send CEO blog to media contacts" {
depends !!!LaunchPhase.final {gaplength 1d}
}
}
}
} # Bitter End
include "reports.tji"
tagfile "tags"