* This file contains an example project. It is part of the
|
|
* TaskJuggler project management tool. It uses a made up software
|
|
* development project to demonstrate some of the basic features of
|
|
* TaskJuggler. Please see the TaskJuggler manual for a more detailed
|
|
* description of the various syntax elements.
|
|
*/
|
|
project acso "Accounting Software" 2002-01-16 +4m {
|
|
# Set the default time zone for the project. If not specified, UTC
|
|
# is used.
|
|
timezone "Europe/Paris"
|
|
# Hide the clock time. Only show the date.
|
|
timeformat "%Y-%m-%d"
|
|
# Use US format for numbers
|
|
numberformat "-" "" "," "." 1
|
|
# Use US financial format for currency values. Don't show cents.
|
|
currencyformat "(" ")" "," "." 0
|
|
# Pick a day during the project that will be reported as 'today' in
|
|
# the project reports. If not specified, the current day will be
|
|
# used, but this will likely be outside of the project range, so it
|
|
# can't be seen in the reports.
|
|
now 2002-03-05-13:00
|
|
# The currency for all money values is the US Dollar.
|
|
currency "USD"
|
|
|
|
# We want to compare the baseline scenario to one with a slightly
|
|
# delayed start.
|
|
scenario plan "Plan" {
|
|
scenario delayed "Delayed"
|
|
}
|
|
extend resource {
|
|
text Phone "Phone"
|
|
}
|
|
}
|
|
|
|
# This is not a real copyright for this file. It's just used as an example.
|
|
copyright "© 2002 Crappy Software, Inc."
|
|
|
|
# The daily default rate of all resources. This can be overridden for each
|
|
# resource. We specify this, so that we can do a good calculation of
|
|
# the costs of the project.
|
|
rate 390.0
|
|
|
|
# Register Good Friday as a global holiday for all resources.
|
|
leaves holiday "Good Friday" 2002-03-29
|
|
flags team
|
|
|
|
# This is one way to form teams
|
|
macro allocate_developers [
|
|
allocate dev1
|
|
allocate dev2
|
|
allocate dev3
|
|
]
|
|
|
|
# In order to do a simple profit and loss analysis of the project we
|
|
# specify accounts. One for the development costs, one for the
|
|
# documentation costs, and one account to credit the customer payments
|
|
# to.
|
|
account cost "Project Cost" {
|
|
account dev "Development"
|
|
account doc "Documentation"
|
|
}
|
|
account rev "Payments"
|
|
# The Profit&Loss analysis should be rev - cost accounts.
|
|
balance cost rev
|
|
|
|
resource boss "Paul Henry Bullock" {
|
|
email "phb@crappysoftware.com"
|
|
Phone "x100"
|
|
rate 480
|
|
}
|
|
resource dev "Developers" {
|
|
managers boss
|
|
resource dev1 "Paul Smith" {
|
|
email "paul@crappysoftware.com"
|
|
Phone "x362"
|
|
rate 350.0
|
|
}
|
|
resource dev2 "Sébastien Bono" {
|
|
email "SBono@crappysoftware.com"
|
|
Phone "x234"
|
|
}
|
|
resource dev3 "Klaus Müller" {
|
|
email "Klaus.Mueller@crappysoftware.com"
|
|
Phone "x490"
|
|
leaves annual 2002-02-01 - 2002-02-05
|
|
}
|
|
flags team
|
|
}
|
|
resource misc "The Others" {
|
|
managers boss
|
|
resource test "Peter Murphy" {
|
|
email "murphy@crappysoftware.com"
|
|
Phone "x666"
|
|
limits { dailymax 6.4h }
|
|
rate 310.0
|
|
}
|
|
resource doc "Dim Sung" {
|
|
email "sung@crappysoftware.com"
|
|
Phone "x482"
|
|
rate 300.0
|
|
leaves annual 2002-03-11 - 2002-03-16
|
|
}
|
|
|
|
flags team
|
|
}
|
|
|
|
# Now we specify the work packages. The whole project is described as
|
|
# a task that contains subtasks. These subtasks are then broken down
|
|
# into smaller tasks and so on. The innermost tasks describe the real
|
|
# work and have resources allocated to them. Many attributes of tasks
|
|
# are inherited from the enclosing task. This saves you a lot of typing.
|
|
task AcSo "Accounting Software" {
|
|
|
|
# All work-related costs will be booked to this account unless the
|
|
# subtasks specify something different.
|
|
chargeset dev
|
|
# For the duration of the project we have running cost that are not
|
|
# included in the labor cost.
|
|
charge 170 perday
|
|
responsible boss
|
|
|
|
task spec "Specification" {
|
|
# The effort to finish this task is 20 man-days.
|
|
effort 20d
|
|
# Now we use the macro declared above to allocate the resources
|
|
# for this task. Because they can work in parallel, they may finish this
|
|
# task earlier than in 20 working-days.
|
|
${allocate_developers}
|
|
# Each task without subtasks must have a start or an end
|
|
# criterion and a duration. For this task we use a reference to a
|
|
# milestone defined further below as the start criterion. So this task
|
|
# can not start before the specified milestone has been reached.
|
|
# References to other tasks may be relative. Each exclamation mark (!)
|
|
# means 'in the scope of the enclosing task'. To descent into a task, the
|
|
# fullstop (.) together with the id of the tasks have to be specified.
|
|
depends !deliveries.start
|
|
}
|
|
|
|
task software "Software Development" {
|
|
|
|
# The software is the most critical task of the project. So we set
|
|
# the priority of this task (and all its subtasks) to 1000, the top
|
|
# priority. The higher the priority, the more likely the task will
|
|
# get the requested resources.
|
|
priority 1000
|
|
|
|
# All subtasks depend on the specification task.
|
|
depends !spec
|
|
|
|
responsible dev1
|
|
task database "Database coupling" {
|
|
effort 20d
|
|
allocate dev1, dev2
|
|
journalentry 2002-02-03 "Problems with the SQL Libary" {
|
|
author dev1
|
|
alert yellow
|
|
summary -8<-
|
|
We ran into some compatibility problems with the SQL
|
|
Library.
|
|
->8-
|
|
details -8<-
|
|
We have already contacted the vendor and are now waiting for
|
|
their advise.
|
|
->8-
|
|
}
|
|
}
|
|
|
|
task gui "Graphical User Interface" {
|
|
effort 35d
|
|
# This task has taken 5 man-days more than originally planned.
|
|
# We record this as well, so that we can generate reports that
|
|
# compare the delayed schedule of the project to the original plan.
|
|
delayed:effort 40d
|
|
depends !database, !backend
|
|
allocate dev2, dev3
|
|
# Resource dev2 should only work 6 hours per day on this task.
|
|
limits {
|
|
dailymax 6h {
|
|
resources dev2
|
|
}
|
|
}
|
|
}
|
|
|
|
task backend "Back-End Functions" {
|
|
effort 30d
|
|
# This task is behind schedule, because it should have been
|
|
# finished already. To document this, we specify that the task
|
|
# is 95% completed. If nothing is specified, TaskJuggler assumes
|
|
# that the task is on schedule and computes the completion rate
|
|
# according to the current day and the plan data.
|
|
complete 95
|
|
depends !database
|
|
allocate dev1, dev2
|
|
}
|
|
}
|
|
|
|
task test "Software testing" {
|
|
|
|
task alpha "Alpha Test" {
|
|
# Efforts can not only be specified as man-days, but also as
|
|
# man-weeks, man-hours, etc. By default, TaskJuggler assumes
|
|
# that a man-week is 5 man-days or 40 man-hours. These values
|
|
# can be changed, of course.
|
|
effort 1w
|
|
# This task depends on a task in the scope of the enclosing
|
|
# task's enclosing task. So we need two exclamation marks (!!)
|
|
# to get there.
|
|
depends !!software
|
|
allocate test, dev2
|
|
note "Hopefully most bugs will be found and fixed here."
|
|
journalentry 2002-03-01 "Contract with Peter not yet signed" {
|
|
author boss
|
|
alert red
|
|
summary -8<-
|
|
The paperwork is stuck with HR and I can't hunt it down.
|
|
->8-
|
|
details -8<-
|
|
If we don't get the contract closed within the next week,
|
|
the start of the testing is at risk.
|
|
->8-
|
|
}
|
|
}
|
|
|
|
task beta "Beta Test" {
|
|
effort 4w
|
|
depends !alpha
|
|
allocate test, dev1
|
|
}
|
|
}
|
|
|
|
task manual "Manual" {
|
|
effort 10w
|
|
depends !deliveries.start
|
|
allocate doc, dev3
|
|
purge chargeset
|
|
chargeset doc
|
|
journalentry 2002-02-28 "User manual completed" {
|
|
author boss
|
|
summary "The doc writers did a really great job to finish on time."
|
|
}
|
|
}
|
|
|
|
task deliveries "Milestones" {
|
|
|
|
# Some milestones have customer payments associated with them. We
|
|
# credit these payments to the 'rev' account.
|
|
purge chargeset
|
|
chargeset rev
|
|
|
|
task start "Project start" {
|
|
# A task that has no duration is a milestone. It only needs a
|
|
# start or end criterion. All other tasks depend on this task.
|
|
# Here we use the built-in macro ${projectstart} to align the
|
|
# start of the task with the above specified project time frame.
|
|
start ${projectstart}
|
|
# For some reason the actual start of the project got delayed.
|
|
# We record this, so that we can compare the planned run to the
|
|
# delayed run of the project.
|
|
delayed:start 2002-01-20
|
|
# At the beginning of this task we receive a payment from the
|
|
# customer. This is credited to the account associated with this
|
|
# task when the task starts.
|
|
charge 21000.0 onstart
|
|
}
|
|
|
|
task prev "Technology Preview" {
|
|
depends !!software.backend
|
|
charge 31000.0 onstart
|
|
note "All '''major''' features should be usable."
|
|
}
|
|
|
|
task beta "Beta version" {
|
|
depends !!test.alpha
|
|
charge 13000.0 onstart
|
|
note "Fully functional, may contain bugs."
|
|
}
|
|
|
|
task done "Ship Product to Customer" {
|
|
# The next line can be uncommented to trigger a warning about
|
|
# the project being late. For all tasks, limits for the start and
|
|
# end values can be specified. Those limits are checked after the
|
|
# project has been scheduled. For all violated limits a warning
|
|
# is issued.
|
|
# maxend 2002-04-17
|
|
depends !!test.beta, !!manual
|
|
charge 33000.0 onstart
|
|
note "All priority 1 and 2 bugs must be fixed."
|
|
}
|
|
}
|
|
}
|
|
|
|
# Now the project has been specified completely. Stopping here would
|
|
# result in a valid TaskJuggler file that could be processed and
|
|
# scheduled. But no reports would be generated to visualize the
|
|
# results.
|
|
|
|
navigator navbar {
|
|
hidereport @none
|
|
}
|
|
|
|
macro TaskTip [
|
|
tooltip istask() -8<-
|
|
'''Start: ''' <-query attribute='start'->
|
|
'''End: ''' <-query attribute='end'->
|
|
----
|
|
'''Resources:'''
|
|
|
|
<-query attribute='resources'->
|
|
----
|
|
'''Precursors: '''
|
|
|
|
<-query attribute='precursors'->
|
|
----
|
|
'''Followers: '''
|
|
|
|
<-query attribute='followers'->
|
|
->8-
|
|
]
|
|
|
|
textreport frame "" {
|
|
header -8<-
|
|
== Accounting Software Project ==
|
|
<[navigator id="navbar"]>
|
|
->8-
|
|
footer "----"
|
|
textreport index "Overview" {
|
|
formats html
|
|
center '<[report id="overview"]>'
|
|
}
|
|
|
|
textreport "Status" {
|
|
formats html
|
|
center -8<-
|
|
<[report id="status.dashboard"]>
|
|
----
|
|
<[report id="status.completed"]>
|
|
----
|
|
<[report id="status.ongoing"]>
|
|
----
|
|
<[report id="status.future"]>
|
|
->8-
|
|
}
|
|
|
|
textreport development "Development" {
|
|
formats html
|
|
center '<[report id="development"]>'
|
|
}
|
|
|
|
textreport "Deliveries" {
|
|
formats html
|
|
center '<[report id="deliveries"]>'
|
|
}
|
|
|
|
textreport "ContactList" {
|
|
formats html
|
|
title "Contact List"
|
|
center '<[report id="contactList"]>'
|
|
}
|
|
textreport "ResourceGraph" {
|
|
formats html
|
|
title "Resource Graph"
|
|
center '<[report id="resourceGraph"]>'
|
|
}
|
|
}
|
|
|
|
# A traditional Gantt chart with a project overview.
|
|
taskreport overview "" {
|
|
header -8<-
|
|
=== Project Overview ===
|
|
|
|
The project is structured into 3 phases.
|
|
|
|
# Specification
|
|
# <-reportlink id='frame.development'->
|
|
# Testing
|
|
|
|
=== Original Project Plan ===
|
|
->8-
|
|
columns bsi { title 'WBS' },
|
|
name, start, end, effort, cost,
|
|
revenue, chart { ${TaskTip} }
|
|
# For this report we like to have the abbreviated weekday in front
|
|
# of the date. %a is the tag for this.
|
|
timeformat "%a %Y-%m-%d"
|
|
loadunit days
|
|
hideresource @all
|
|
balance cost rev
|
|
caption 'All effort values are in man days.'
|
|
|
|
footer -8<-
|
|
=== Staffing ===
|
|
|
|
All project phases are properly staffed. See [[ResourceGraph]] for
|
|
detailed resource allocations.
|
|
|
|
=== Current Status ===
|
|
|
|
The project started off with a delay of 4 days. This slightly affected
|
|
the original schedule. See [[Deliveries]] for the impact on the
|
|
delivery dates.
|
|
->8-
|
|
}
|
|
|
|
# Macro to set the background color of a cell according to the alert
|
|
# level of the task.
|
|
macro AlertColor [
|
|
cellcolor plan.alert = 0 "#00D000" # green
|
|
cellcolor plan.alert = 1 "#D0D000" # yellow
|
|
cellcolor plan.alert = 2 "#D00000" # red
|
|
]
|
|
|
|
taskreport status "" {
|
|
columns bsi { width 50 title 'WBS' }, name { width 150 },
|
|
start { width 100 }, end { width 100 },
|
|
effort { width 100 },
|
|
alert { tooltip plan.journal
|
|
!= '' "<-query attribute='journal'->" width 150 },
|
|
status { width 150 }
|
|
scenarios delayed
|
|
|
|
taskreport dashboard "" {
|
|
headline "Project Dashboard (<-query attribute='now'->)"
|
|
columns name { title "Task" ${AlertColor} width 200},
|
|
resources { width 200 ${AlertColor}
|
|
listtype bullets
|
|
listitem "<-query attribute='name'->"
|
|
start ${projectstart} end ${projectend} },
|
|
alerttrend { title "Trend" ${AlertColor} width 50 },
|
|
journal { width 350 ${AlertColor} }
|
|
journalmode status_up
|
|
journalattributes headline, author, date, summary, details
|
|
hidetask ~hasalert(0)
|
|
sorttasks alert.down, delayed.end.up
|
|
period %{${now} - 1w} +1w
|
|
}
|
|
taskreport completed "" {
|
|
headline "Already completed tasks"
|
|
hidetask ~(delayed.end <= ${now})
|
|
}
|
|
taskreport ongoing "" {
|
|
headline "Ongoing tasks"
|
|
hidetask ~((delayed.start <= ${now}) & (delayed.end > ${now}))
|
|
}
|
|
taskreport future "" {
|
|
headline "Future tasks"
|
|
hidetask ~(delayed.start > ${now})
|
|
}
|
|
}
|
|
|
|
# A list of tasks showing the resources assigned to each task.
|
|
taskreport development "" {
|
|
scenarios delayed
|
|
headline "Development - Resource Allocation Report"
|
|
columns bsi { title 'WBS' }, name, start, end, effort { title "Work" },
|
|
duration, chart { ${TaskTip} scale day width 500 }
|
|
timeformat "%Y-%m-%d"
|
|
hideresource ~(isleaf() & isleaf_())
|
|
sortresources name.up
|
|
}
|
|
|
|
# A list of all tasks with the percentage completed for each task
|
|
taskreport deliveries "" {
|
|
headline "Project Deliverables"
|
|
columns bsi { title 'WBS' }, name, start, end, note { width 150 }, complete,
|
|
chart { ${TaskTip} }
|
|
taskroot AcSo.deliveries
|
|
hideresource @all
|
|
scenarios plan, delayed
|
|
}
|
|
# A list of all employees with their contact details.
|
|
resourcereport contactList "" {
|
|
scenarios delayed
|
|
headline "Contact list and duty plan"
|
|
columns name,
|
|
email { celltext 1 "[mailto:<-email-> <-email->]" },
|
|
Phone,
|
|
managers { title "Manager" },
|
|
chart { scale day }
|
|
hideresource ~isleaf()
|
|
sortresources name.up
|
|
hidetask @all
|
|
}
|
|
|
|
# A graph showing resource allocation. It identifies whether each
|
|
# resource is under- or over-allocated for.
|
|
resourcereport resourceGraph "" {
|
|
scenarios delayed
|
|
headline "Resource Allocation Graph"
|
|
columns no, name, effort, rate, weekly { ${TaskTip} }
|
|
loadunit shortauto
|
|
# We only like to show leaf tasks for leaf resources.
|
|
hidetask ~(isleaf() & isleaf_())
|
|
sorttasks plan.start.up
|
|
}
|
|
|